Drone photo of Park Bridge completed in 2015 in Kicking Horse Canyon shows challenge of highway widening through the Rocky Mountains. (Ministry of Transportation)

Kicking Horse widening budget up $151 million as bidders invited

Union-only construction adds 5.8% to price of B.C.’s toughest project

B.C.’s transportation ministry is inviting bids to design and build the most difficult highway project in the province’s history, with costs going up, mainly due to union-only construction and engineering changes.

The latest cost estimate for the fourth phase of the Kicking Horse Canyon widening project is $601 million, a $151 million increase since the 2016 project budget. The ministry estimates that $35 million of that is to implement the NDP government’s “community benefits agreement” for public construction projects, requiring worker membership in approved building trades unions.

Other increased costs include additional geotechnical and other engineering work, additional foundation supports for bridges and retaining walls, consultation with Indigenous communities and a bigger contingency fund due to the risk and complexity of the project.

Phase four is four-laning of the final section of Kicking Horse Canyon east of Golden, 4.8 km from West Portal to Yoho Bridge. Construction is slated to begin in the summer of 2020, with completion by the winter of 2023-24.

The cost increase also includes an additional $23 million in interest charges, since the project was initially approved with a $450 million price tag in 2015.

Transportation Minister Claire Trevena emphasized the safety improvement needed in the Kicking Horse Canyon, which has an accident rate three times the average for B.C. highways and areas with effectively no shoulder for vehicles to pull off in an emergency.

RELATED: B.C. Highway 1 widening demanded for decades

RELATED: Single-bridge option chosen for Sicamous section

The average speed for the existing canyon road is 55-65 km/h, causing long backups behind transport trucks and recreational vehicles winding through the scenic route. The objective of the widening is to get the average speed up to 100 km/h as well as enhance safety.

The project will require closure of the Trans Canada Highway from Castle Junction to Golden for an estimated total of 15 weeks. A detour route using Highway 93 and 95 through Radium Hot Springs will add 104 km to the route, approximately an hour and a half of additional travel time.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Students cash in on awards for Legion Literary and Poster Contest

Chemainus branch rewards exceptional artistic work and writing

Snowy scenes

The white stuff makes a dramatic appearance

What happens in the Cowichan Valley when an earthquake strikes

When an earthquake does happen, will the Cowichan Valley be ready for it?

Winter storm warning now in effect for Island’s east coast

Environment Canada issues new weather warning late Wednesday afternoon

After cashing in on QB gambles, Chiefs and 49ers to clash in Super Bowl

KC beats Tennessee, San Francisco dispatches Green Bay to reach NFL title game

B.C. VIEWS: Few clouds on Horgan’s horizon

Horgan’s biggest challenge in the remainder of his term will be to keep the economy humming along

Victoria family focuses on ‘letting go, enjoying time together’ after dad gets dementia

Walter Strauss has developed an interest in music and now takes line dancing classes

B.C. forest industry grasps for hope amid seven-month strike, shutdowns, changes

Some experts say this could be worse for forestry than the 2008 financial crisis

Northern B.C. RCMP investigating alleged sexual assault in downtown Smithers

One person was transported by ambulance to hospital following RCMP investigation at Sedaz

UBC, Iranian-Canadian community create memorial scholarship in honour of victims

The Jan. 8 crash killed 176 people, including 57 Canadians

Disrespectful that Horgan won’t meet during northern B.C. tour: hereditary chief

Na’moks said he was frustrated Horgan didn’t meet with the chiefs

Most Read